Work package bill of quantities
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor), that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers to allow them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities:
- Elemental bill of quantities.
- Work package bill of quantities.
- Work section bill of quantities.
The work package breakdown structure undertakes measurement and description divided into employer, quantity surveyor or contractor defined work packages (based either on a specific-trade, or a single package comprising a number of different trades). This structure may be preferred by contractors for procuring from their supply chain.
NRM 2 suggests that a typical breakdown structure for a discrete work package might be:
- Bill No. 1: Main contractor’s preliminaries.
- Bill No. 2: Intrusive investigations.
- Bill No. 3: Demolition works.
- Bill No. 4: Groundworks.
- Bill No. 5: Piling.
- Bill No. 6: Concrete works.
- Bill No. 7: Roof coverings and roof drainage.
- Bill No. 8: External and internal structural walls.
- Bill No. 9: Cladding.
- Bill No. 10: Windows and external doors.
- Bill No. 11: Mastic.
- Bill No. 12: Non-structural walls and partitions.
- Bill No. 13: Joinery.
- Bill No. 14: Suspended ceilings.
- Bill No. 15: Architectural metalwork.
- Bill No. 16: Tiling.
- Bill No. 17: Painting and decorating.
- Bill No. 18: Floor coverings.
- Bill No. 19: Fittings, furnishings and equipment.
- Bill No. 20: Combined mechanical and electrical engineering services.
- Bill No. 21: Lifts and escalators.
- Bill No. 22: Facade access equipment.
- Bill No. 23: External works and drainage.
- Bill No. 24: Risks.
- Bill No. 25: Provisional sums.
- Bill No. 26: Credits.
- Bill No. 27: Daywork (Provisional).
[edit] Related articles on Designing Buildings
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Facade access equipment.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Schedule of rates.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Work section bill of quantities.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.